PROGRAMME OF ACTIVITIES
ITEM No.ONE. Activities/ Duration ---------------------- 1 wk
Preparation for dismantling,
-Disassembling of G399/G3512 Cat engine
Preparation of storage equipment and -procedure and specification containing the
dismantling of accessories, -process materials and tools.
-lifting devices and positioning structures fabrication.
-transporting and transferring of plant to W/Shop.
No..TWO. Activities Duration --------------------------- 1wk
Component and Material procurement procurement for malfunctioned parts/components
and other accessories.
No. Three. Activities Duration--------------------------- 3wks Process of metro-logical Inspection Preparation and assembling.
Pressure testing and of cylinders i) measurement of crankshaft journals
- hydro-testing of cylinders ii) measurement of ovality and inspection
- hydro-testing of oil coolers iii)measurement of connecting rod
-inspection and test of heat exchanger iv)placement of components on appropriate work instrument on benches benches for assembly and selection