Priority system for planning and scheduling of all maintenance work are as follows and are arranged in order of priority as shown below
Production Assisted work description Maintenance Assisted work description
10. Equipment which will shut down the entire plant 9. Breakdown safety hazards where loss
if not operating .All safety work orders. of life or limb is probable. 8. Equipment that will shut down an entire department 7. Preventive maintenance production
if not operating.
- assistance.maintenance perform
ed during production.
- 6 Equipment that will reduce the output of the 5 Repair to major parts or units that are
department if not running. Equipment that will shutdown not running.Shut down of a department
an entire department if not running ,when installed spares or major system Normal are available for immediate operation. health and safety work.
ment that is important to the operation of a
3.Shop work or other routinework a department but will not shut down the department of
4.Auxiliary equip non repairs due to spare parts or units are
cause a major loss if not operating. available for immediate production runs
.
2.Convenient items,cost saving equipment ,
building roads 1.Painting for appearance or protection.
The use of skill crafts for cleanup . other than their work
.
To set up the PS system,identify every piece of equipment in the plant with production assigned even numbers published this list to all concerned and ascertain they thoroughly understand the concept.The production number should then be identified,on every work order in the case of dual purpose equipment or debatable number consider the productivity of the product and production schedules in assigning the production numbers. The production number can be change several times in a year to handle seasonal work and drastic changes in schedules.(Beachleg,1995.).