The network analysis for engine assembling and disassembling is used for evaluation of duration of project period,which may involved the following,1. early start, 2.late finish, 3.activity nodes, other activity are: 4.Mobilization
5.Main components dismantling.
6.Engine accessories dismantling
7.Bedding/Inspection
8.Kitting of components.
9.Testing and calibration of accessories.
10.Reassembling of components/Torque/Painting
11.Crank and testing.
12.Test Run on Load/Performance Test.
13.Commissioning/Demobilization.
14.Duration.
No comments:
Post a Comment